Today’s poster
What to note today
- 01
- 02
- 03
- 04
Popular searches
Quantitative Aptitude · 20 min read
Time and Work has a reputation for fiddly fractions, and it is entirely undeserved. Adding 1/12 and 1/18 under exam pressure is slow and error-prone, but the same question in whole units — the LCM method — is mental arithmetic.
This page teaches that method first and then uses it for everything else: pipes and cisterns, efficiency ratios, alternate-day working and wage sharing are all the same setup with a different label. Learn one technique properly and the topic collapses to a single skill.
Current affairs · 19 September 2026
Every item is dated, read on the conducting body’s or ministry’s own site, and written with the question it becomes. Read today’s items, take the quiz, or download the month as a PDF.
Today’s poster
Why it matters
| Exam | Expected questions | How it usually appears |
|---|---|---|
| SSC CGL / CHSL Tier 1 | 2–4 questions | Usually one straight work question and one pipes-and-cisterns. |
| Banking Prelims & Mains | 2–3 questions | Often as a two-statement sufficiency or a caselet. |
| RRB NTPC / Group D | 3–4 questions | Direct man-days and combined-work questions. |
| CAT / MBA entrances | 1–3 questions | Mixed groups of men and women, or variable efficiency. |
Start here
The whole topic rests on one move: convert "days to finish" into "work done per day". Times cannot be added; rates can.
Averaging the two times is the standard trap and the answer examiners put first in the options. If A takes 10 days and B takes 15, the pair must finish in fewer than 10 — two people are faster than the faster one alone. Any answer above the smallest individual time is wrong on its face.
Learn this properly
Instead of calling the job "1" and working in fractions, call it the LCM of all the times given. Every rate then becomes a whole number, and the arithmetic stops being the hard part.
The method is three steps. Take the LCM of every time in the question and call that the total work. Divide it by each person's time to get their daily output in units. Then add, subtract or scale those whole numbers as the question requires.
A can do a piece of work in 12 days and B in 18 days. How long will they take together?
Answer: 7.2 days, or 7 1/5 days.
The fraction route needs 1/12 + 1/18 = 5/36 and then a reciprocal. The LCM route needs 3 + 2 = 5. Both give the same answer, but only one is safe to do in your head with a clock running — and the units carry through unchanged when the question adds a third worker or a leak.
Core skill
Once rates are whole numbers, combining workers is addition and removing one is subtraction. The reverse question — given the pair, find one alone — is the same operation backwards.
A and B together finish a job in 8 days. A alone takes 12 days. How long does B take alone?
Answer: B alone takes 24 days.
Inverse relationship
Efficiency is work per day, so it is inversely proportional to the time taken. A worker twice as efficient takes half as long — and the ratio flips.
A is twice as efficient as B, and together they finish a job in 8 days. How long would A take alone?
Answer: A alone takes 12 days. (B alone would take 24.)
Exam classic
When the number of workers changes, the total labour required stays fixed. That constant is the man-days — or man-hours, if hours per day are involved.
8 men can complete a job in 6 days working 8 hours a day. How many days will 4 men take working 12 hours a day?
Answer: 8 days.
Same topic, new label
A pipe filling a tank is a worker doing a job. The only new idea is that an outlet pipe or a leak works at a negative rate.
Pipe A fills a tank in 6 hours, pipe B in 8 hours, and pipe C empties it in 12 hours. If all three are open, how long does the tank take to fill?
Answer: 4.8 hours, or 4 hours 48 minutes.
A tap fills a tank in 8 hours, but because of a leak it takes 12 hours. How long would the leak alone take to empty a full tank?
Answer: 24 hours.
Question shapes
Two variations that look harder than they are. In units, both reduce to counting how much work is done and how much is left.
A can do a job in 20 days and B in 30 days. They work together for 5 days, then A leaves. How long does B take to finish?
Answer: 17.5 days more.
Straightforward marks
Payment is proportional to work actually done. When everyone works for the whole job, that means payment is proportional to efficiency.
A, B and C together complete a job and are paid ₹1 800. Alone they would take 6, 8 and 12 days. How is the money shared?
Answer: A gets ₹800, B ₹600 and C ₹400.
Solved examples
Read the steps rather than the answer. The method is what transfers to the next question.
12 men can complete a work in 15 days. How many days will 20 men take?
Answer: 9 days.
A can do a job in 10 days and B in 15 days. Working on alternate days starting with A, how long does the job take?
Answer: 12 days.
A alone can finish a work in 18 days. He works for 6 days and leaves; B finishes the rest in 12 days. How long would B alone take?
Answer: 18 days.
Two pipes fill a tank in 20 and 30 minutes. How long do they take together?
Answer: 12 minutes.
A, B and C can do a work in 10, 12 and 15 days. How long together?
Answer: 4 days.
A can do half a work in 5 days and B can do a third of it in 4 days. How long will they take together?
Answer: 60/11 days, which is 5 5/11 days.
6 men and 8 women finish a job in 10 days, while 26 men and 48 women finish it in 2 days. How long will 15 men and 20 women take?
Answer: 4 days.
If 5 men or 8 women can do a work in 12 days, how long will 2 men and 4 women take?
Answer: 13.33 days, or 13 1/3 days.
12 men start a job that should take 20 days. After 8 days, 4 more men join. When is the job finished?
Answer: 17 days.
A and B can do a work in 6 and 8 days. With C they finish it in 3 days. How long would C alone take?
Answer: 24 days.
Practice
Work each one out before you reveal the answer — the explanation is where the marks are.
Q1A does a work in 15 days and B in 10 days. Together they take:
Q2A and B together finish a job in 12 days; B alone takes 20 days. A alone takes:
Q310 men can complete a work in 12 days. 15 men will take:
Q4A is three times as efficient as B and together they finish in 9 days. B alone would take:
Q5A pipe fills a tank in 10 hours while a leak empties it in 15 hours. With both open the tank fills in:
Q6A and B take 20 and 25 days alone. After working together for 5 days, the fraction of work left is:
Q78 men complete a job in 6 days working 8 hours a day. 4 men working 12 hours a day will take:
Q8A, B and C can do a work in 10, 12 and 15 days respectively. Together they take:
Q9A does half a work in 5 days and B does a third of it in 4 days. Together they finish the whole work in:
Q10A and B finish a job together and are paid ₹3 000. Alone they would take 12 and 18 days. A receives:
Q11Two pipes fill a tank in 20 and 30 minutes. Opened together, the tank fills in:
Q12A alone takes 18 days. He works 6 days and leaves; B finishes the rest in 12 days. B alone would take:
Q13A is twice as good a workman as B, and together they finish in 14 days. A alone would take:
Q14A tap fills a tank in 8 hours but takes 12 hours because of a leak. The leak alone empties a full tank in:
Q1512 men start a 20-day job. After 8 days, 4 more men join. The job is completed in a total of:
Q16A and B do a work in 6 and 8 days. With C they finish in 3 days. C alone would take:
Questions
Instead of calling the job "1" and working in fractions, call it the LCM of every time in the question. Each worker's daily output then becomes a whole number. For times of 12 and 18 days, the job is 36 units and the rates are 3 and 2 a day — so together they do 5 a day and finish in 7.2 days.
Because times cannot be averaged — only rates add. Two people working together must be faster than the faster one alone, so any answer above 10 days is wrong on its face. The correct working is 1/10 + 1/15 = 1/6, giving 6 days.
They are inversely proportional. If A is three times as efficient as B, A takes a third of the time, and the efficiency ratio 3 : 1 corresponds to a time ratio of 1 : 3. Whenever a question gives you one, write down the other immediately.
Only in sign. An inlet pipe is a worker with a positive rate; an outlet pipe or a leak has a negative one. Add all the rates and the sign of the total tells you whether the tank fills or empties. Everything else — the LCM method included — is unchanged.
M₁D₁H₁/W₁ = M₂D₂H₂/W₂, where M is the number of workers, D the days, H the hours per day and W the amount of work. Drop H when hours are not mentioned and W when the job is the same, which reduces it to M₁D₁ = M₂D₂.
Work out how much is done in one complete two-day cycle, then see how many cycles fit into the total. If A does 3 units and B 2, a cycle produces 5 units, so a 30-unit job needs six cycles — 12 days. Always check whether the job finishes partway through the last cycle.
In proportion to the work each person actually did, never to the time they spent. If three workers who would take 6, 8 and 12 days alone all work throughout, their rates are 4 : 3 : 2 and the money splits in that ratio.
Set up two equations from the two given combinations and eliminate one variable to find how many women equal one man. Once you have that conversion, express the whole team in a single unit and use the man-days idea as normal.
Multiply the combined rate by the days worked to get units completed, then subtract from the total. Working in LCM units keeps this as whole-number subtraction; dividing at the end converts it back to a fraction if the question wants one.
Expect two to four questions in SSC CGL and CHSL, three to four in RRB NTPC, and two to three in banking — usually one straight work question plus one on pipes and cisterns. With the LCM method it is among the fastest topics to score in.
Keep going
Attempt a timed mock while the formulas are fresh — that is what tells you which of them actually stuck.
Already practising? Create Free Account to track your preparation.